December 2025 – Pool & Restrooms Refurbishment

Please click on the first image to view as a slide show.

 

Pool deck prior to job commencement
Pool furniture removed
Pool deck being power washed

Corrections to existing concrete in disrepair
Corrections to existing concrete in disrepair
Patch repair finished with texture to match existing adjacent texture

Sealants applied to smaller fractures
Meticulous and conscientious corrections to existing concrete surface
Meticulous and conscientious corrections to existing concrete surface

Application of color sealant
Repair, primer and paint of pool storage shed
Storage shed completed

Section of pool deck with new color sealer applied
Team work – Getting it done!
Beautiful finished section of pool deck

Pool furniture back in place – Pool deck done
Men’s restroom prior to work commencement
Ladies’ restroom prior to work commencement

Ladies’ restroom prior to work commencement
Ladies’ restroom prior to work commencement - cubicle size was too small and not acceptable
Partitions removed at ladies’

Wall tile being removed
Tile and partitions removed at ladies
Concrete being cut to accommodate toilet relocation and larger cubicles

Floor concrete and wall plaster removed, plumbing rough in done
Rebar installed and dowelled into adjacent existing concrete floor
Concrete installation

Floor concrete finished and wall lath installed
Plaster scratch coat and ceiling drywall installed
Plaster brown coat and drywall mud installed

Plaster demolition to accommodate in wall towel dispenser and trash
Wall framing being tailored to accommodate new in-wall towel dispenser
New casing installed at recessed lighting

Plaster install at walls
Walls and ceiling texture application
Wall and ceiling, prime and painting

New ceiling light fan installations with ducting corrections in attic
Walls and ceilings painted
Texture application being sprayed on floor

Texture application being knocked down
Floor color sealer starting to be applied over knock down floor texture
Floor completed at ladies

Floor completed at men’s
Plumbers installing new toilets at ladies
New toilet locations accommodating larger cubicle area

New toilets and sink at men’s
New partitions and stainless-steel accessories installed at men’s – job done
New partitions and stainless-steel accessories at ladies

12►

 

 

 

← Nov 2025 - Balcony Drainage Corrections Dec 2025 - Landscape Drainage →
View all Projects
Contact Us

General Contractor serving Southern California since 1992 providing reconstruction, remodel and repair for Homeowners Associations (HOAs), Residential and Commercial projects.

© 2026 Angus Smith Construction

Contractors License #637440