November 2021 – Foundation Replacement

Please click on the first image to view as a slide show.

Right side of garage prior to job commencement
Left side of garage prior to job commencement
Garage foundation in poor condition at left side prior to job commencement

Drywall removed and damaged stem foundation at right side of garage
Shoring being installed at left side of garage
Shoring being installed at left side of garage

Shoring completed at left side of garage
Shoring completed at right side of garage. Garage structure is now completely supported and ready to accommodate foundation repairs
Shoring completed at right side of garage Garage structure is now completely supported and ready to accommodate foundation repairs

Stucco removal at right side of garage
Some muscle required to remove 15” wide footing at front of garage
Foundation stem being removed at left side of garage

Existing foundation tied in with rebar. Separating and removing is no easy task
Existing foundation stem remvoed and holes being drilled to accommodate new dowelled rods
After deputy inspection, dowelled holes filled with ‘ Two Part High Strength Epoxy Anchoring Adhesive ‘

Anchoring rods being installed into epoxy filled holes
Exterior concrete forms installed at left side of garage
Horizontal rebar tied to dowelled anchoring rods set in epoxy at front left side of garage. Rebar with epoxy coating to minimize future corrosion

Close up view of engineered detail for concrete re-enforcement
Concrete adhesive being applied to strengthen bond of new to existing concrete
New concrete being installed at front left side of garage- new footing being spoon fed !

Concrete installation
Concrete form removed and finishing process being done
Beautiful new concrete foundation stem finished with edge bevel. Anchor rods plated and top nuts tightened

Exterior concrete forms removed
Galvanized stucco weep screed installation
New building paper and stucco lath installed

First coat of plaster / scratch coat installed at right side of garage
Second coat of plaster / brown coat installed at left front of garage
Finish stucco coat being applied

Stucco coat applied with knock down texture at left front of garage
Stucco coat applied with knock down texture at right side of garage
Stucco coat applied with knock down texture at left side of garage

Primer application at new stucco
Drywall being installed inside garage
Drywall being finished

Drywall hung, taped and mud application done at right side
Beautiful new stem foundation and drywall at right side of garage
Job done at left side of garage

Stucco painted to match existing at left side exterior. Beautiful match and finish !
Beautiful exterior match and finish at right side of garage !

 

 

← Nov 2021 - Slider Replacement Feb 2022 - Soil Retention Upgrade →