Project Gallery

October 2022 – Balcony & Patio Doors

Please click on the first image to view as a slide show.

Rear of unit prior to construction
Layout for concrete footings and excavation commencement
Footings excavation and oh yes – there has to be a tree at footing location!

Tree root and concrete – foundation synergies!
On site rebar fabrication to strengthen concrete foundations
Steel fabrication per engineer specifications for (4) footing locations

Above grade foundation forms / sono tubes and post base brackets supported with wood framework.  Fabricated steel placed in footing excavation. Ready to pour concrete
Concrete pour
Concrete footings poured

Siding removal commencement at rear of unit
Framing corrections at existing subfloor
Metal z bar flashing and building paper installed at top of existing lower siding

Ledger location prepped and ready for install
Ledger fasteners installed quickly and efficiently with impact wrench
Ledger installed with crawlspace venting incorporated into new ledger

Pressure treated floor joists supported with joist hangers at ledger and by beam on top of concrete footings
Additional hardware and framing required at rim joist locations where balcony railing posts will be located
Metal straps which will attach railing posts to subfloor

Post attachment straps installed at balcony floor perimeter
Bonderised floor to wall and fascia flashing installed at balcony floor perimeter, securing vulnerable locations from moisture penetration
Metal edge flashing notched to accommodate straps

Trex decking notched to accommodate protruding post attachment brackets. Balcony subfloor composite fascia installed
Trex decking installation
Close up view of Trex hidden fastener system and yellow decking spacer

Beautiful Trex Transcends installed
Decay resistant con heart redwood railing posts installed
Rail framing install with pneumatic nailer for speed and efficiency

Pneumatic palm nailer to speed the process of fastening endless California required framing hardware
Rail framing completed
Electrical outlets being installed at rail framing

Electrical conduit below existing window
Electrical conduit removed below window to accommodate new patio doors install
Electrical rough in completed with metal nail stopper plates at each railing support

Waterproof building paper being wrapped on to rail framing
Smart panel siding being cut at 45-degree angle for railing exterior
Exterior railing siding being installed – moistop flashing at top of rail framing

Interior railing siding being installed
Lower rail cap with precision cut out to fit over railing posts
Quality craftsmanship resulting in perfectly aligned corner

Composite lower rail cap being installed
Composite trim, decay resistant treated upper caps (body guard) installed – exterior railing carpentry completed
Interior railing carpentry completed

Siding removed at patio door’s location
Interior view of window prior to replacement with patio doors
Window removed and framing exposed

Existing framing being tailored for new doors
Subfloor framing corrections
Subfloor corrected and leveled to accommodate new doors

12►

 

 

← Jun 2022 - Balcony Construction
View all Projects
Contact Us

General Contractor serving Southern California since 1992 providing reconstruction, remodel and repair for Homeowners Associations (HOAs), Residential and Commercial projects.

© 2023 Angus Smith Construction

Contractors License #637440